Industrial software · PLC · Robotics · Commissioningmail@fiwatec.com
Lifecycle

Commissioning, retrofit & production optimisation

Support for ramp-up, modifications, migrations, troubleshooting and cycle-time optimisation of PLC, robot and production systems.

CommissioningRetrofitPLCRoboticsPROFINETModbusCycle time
Scope

Engineering with the complete system in mind

FIWAtec combines software, commissioning and plant-level understanding. The exact scope is aligned with the installed hardware, standards and production requirements.

  • Initial and recommissioning
  • Plant extensions and modifications
  • PLC and robot migration
  • Interface, fieldbus and vision-system diagnostics
  • Cycle-time and process optimisation
  • Production support and troubleshooting
Automated production cell
Commissioning

From individual signal to automatic operation

I/O, safety releases, bus communication, handshakes and process sequences are tested step by step to create reproducible machine states.

Retrofit

Modernise without losing process knowledge

Existing functions are captured, dependencies documented and migrated in a controlled way to new control or robot generations.

Related

Related services

Commissioning and retrofit bring controls, robotics and supporting industrial software together directly. We coordinate the disciplines so that states, interfaces and tests remain traceable across the complete plant.

01

PLC

Develop or migrate control programs, structure operating modes and sequences, and coordinate fieldbuses, interlocks, diagnostics and restart behaviour.

Learn more →
02

Robotics

Integrate robots, configure programs and tools, optimise paths and handovers, and reliably test communication with PLCs and peripherals.

Learn more →
03

Industrial software

Python and C++ tools, data processing, protocol conversion and interfaces for diagnostics, commissioning, machine connectivity and IT integration.

Learn more →
Project practice

Commissioning and retrofit with controlled test stages

During production ramp-up, software, electrical systems, mechanics, communication and the real process come together fully for the first time. We therefore start from a secured baseline and test the plant from individual signals through operating modes and interfaces to the integrated automatic sequence.

Retrofit work also requires a structured inventory: existing functions, process knowledge and dependencies must be retained while controls, robots, bus components or operator interfaces are renewed. Each stage is prepared so faults can be isolated, changes traced and defined intermediate versions restored if required.

Typical tasks

  • Secure software versions, parameters, programs and hardware configurations
  • Check I/O, safety permissions, fieldbuses, networks and device communication
  • Test manual functions, operating modes, interlocks and local machine functions
  • Integrate robots, vision systems, drives and other peripherals step by step
  • Release automatic steps individually before combining the full plant sequence
  • Test faults, timeouts, communication loss and controlled restart behaviour
  • Document changes, test results, backups, open issues and the handover version

Robust implementation

Baseline & target state

Before the first change, actual machine states, software and hardware versions, interfaces, safety boundaries and known dependencies are recorded. Combined with the required target state, this creates a reliable working and rollback baseline instead of an unsecured assumption.

Explicit states & interfaces

Operating modes, commands, feedback, interlocks, timeouts and fault reactions are structured clearly across system boundaries. This reduces ambiguity, accelerates troubleshooting and makes later maintenance or expansion easier.

Test & handover

We do not test only the ideal sequence. Manual mode, automatic operation, production interruption, component faults, communication loss and restart behaviour are checked within the agreed scope; changes and results are recorded for a traceable handover.

FAQ

Common questions

How does commissioning start?

Commissioning starts with secured software and hardware versions, an agreed test sequence and explicit safety boundaries. Power, I/O, safety permissions and communications are validated first; manual functions, individual automatic steps and the integrated cycle follow. If a deviation occurs, this sequence makes the affected system and test stage clear.

How is retrofit different from a new build?

A retrofit must preserve existing functions, production knowledge and often historically grown interfaces while introducing new technology. Dependencies, special cases and current software versions are therefore captured before migration. Conversion proceeds in controlled stages with backups, rollback options and targeted comparisons between old and new behaviour.

Can work be done during production?

Depending on the task and risk assessment, some analysis or preparation may be possible during production. Changes to control programs, safety functions or integrated sequences require coordinated windows, secured backups and a clear rollback plan. The exact scope is agreed with production, maintenance and the responsible project contacts.

What should be documented after changes?

Documentation should cover the baseline and handover versions, changed functions and parameters, affected interfaces, test results and known open issues. Depending on the project, it also includes program and parameter backups, version records, network or device changes and restart notes. This keeps clear what was changed, tested and released for operation.